|
There are
two basic types of ponds: embankment and excavation.
Embankment
ponds are built by placing an embankment or dam across a stream
or watercourse where the stream valley is depressed enough to permit
storing 5 feet or more of water.
Excavated ponds
are made by digging a pit or dugout in a nearly level area. Because
the water capacity is obtained almost entirely by digging, excavated
ponds are best used where only a small supply of water is needed.
After you've
decided the why of the pond, you need to consider the where.
Selection of the pond site is one of the most important steps
in construction. If possible, consider more than one location and
then evaluate each one's economic, accessibility, and safety factors.
For economy,
locate the pond where the largest storage volume can be obtained
with the least amount of earthfill. Say, in a valley where a dam
can be built across a narrow section where slopes are steep, and
the slope of the valley floor permits a large area to be flooded.
|
|
If
the pond is to be used to water livestock, locate it in or near
each pasture or grazing unit. Forcing livestock to travel long
distances to water is detrimental to both the livestock and
the grazing area. |
| If
the pond water will have to be conveyed for use elsewhere, such
as for irrigation or fire protection, locate the pond close
to the major water use. Conveying water is expensive, so the
shorter the distance, the better. Otherwise it may not be practical. |
|
Ponds intended
for recreational purposes, such as fishing, boating, and swimming,
should be accessible. Income-producing ponds, used by the general
public, must be easily reached by automobile.
Avoid pollution
of pond water by selecting a location where drainage from farmsteads,
feedlots, corrals, sewage lines, mine dumps, and similar areas does
not reach the pond.
Consider the
possibility of failure of the pond's dam and the damage that could
result from the sudden release of water, such as loss of life, injury
to persons or livestock, and damage to homes.
Be sure that
no buried pipelines or cables cross the proposed pond site. If they
do, you must notify the utility company before starting construction
and obtain permission to excavate.
Other factors
to consider:
Adequacy of
the drainage area - For ponds where surface runoff is the main source
of the water, the contributing drainage area must be large enough
to maintain water in the pond during droughts. The physical characteristics
that affect the amount of runoff are relief, soil infiltration,
plant cover, and surface storage. Storm characteristics, such as
amount, intensity, and duration of rainfall, obviously will also
affect runoff.
Minimum pond
depth - To avoid shortages of water, the water must be deep enough
to meet the requirements of its intended use, and to offset probable
seepage and evaporation losses. To estimate pond capacity, use this
simple method:
- Establish
the normal pond-full water elevation and stake the waterline
at this elevation.
- Measure
the width of the valley at this elevation at regular intervals
and use these measurements to computer the pond-full surface
area in acres.
- Multiply
the surface area by 0.4 times the maximum water depth in
feet measured at the dam.
|
Drainage area
protection - To maintain the required depth and capacity of a pond,
the inflow of water must be reasonably free of silt. Land under
permanent cover of trees or vegetation provides the most desirable
drainage area. For cultivated drainage areas, application and maintenance
of erosion control practices is essential to their protection.
Landscape -
To maximize visibility of the pond, locate it so that the major
sight line crosses the longest dimension of water surface. This
way the viewer will see the water before noticing the dam, pipe
inlet, or spillway. Ponds designed around existing vegetation will
help blend the pond into the surroundings. The vegetation will provide
shade on hot days as well as habitat for wildlife.
You've got
your location, and you're ready to build. What's next? It depends
on the type of pond you are building.
Embankment
Ponds
Before beginning
construction of this type of pond, a site survey is needed
to plan and design the dam, spillways, and other features. If you
are not familiar with the use of surveying equipment, consult a
licensed surveyor for this step.
Pond surveys
usually consist of a profile of the centerline of the dam, a profile
of the centerline of the earth spillway, and enough measurements
to estimate pond capacity (see the simple method above). Larger
and more complex ponds may need a complete topographic survey of
the entire pond site.
All surveys
made at the pond site should be tied to a reference called a bench
mark. A bench mark could be a large spike driven into a tree,
an iron rod driven flush with the ground, or any object that will
be undisturbed during and after construction of the dam.
A detailed
investigation of the soils in the pond area is also necessary.
Identifying the soil type(s) in the pond area, will help determine
the soil's ability to hold water and, therefore the suitability
of the pond site. The soil should contain a layer of material the
is impervious and thick enough to prevent excessive seepage. Clays
and silty clays are excellent; coarse-textured sands and sand-gravel
mixes are not. Limestone or shale areas should be avoided because
of possible fractures which create leaks. Swampy areas are poor
sites because they are difficult to drain and costly to maintain.
If there is
a question as to whether the soils in the area are sufficiently
impervious, soil borings should be done over the area to be covered
by water. Three or four borings per acre may be enough if the soils
are uniform. If they prove significantly different, more borings
would be recommended.
The ability
to hold water isn't the only reason to determine the soil type.
The soil will also be providing the foundation for the dam, ensuring
stable support of the structure. Good foundation materials are a
mixture of coarse- and fine-textured soils, such as gravel-sand-clay
mixtures, gravel-sand-silt mixtures, sand-clay mixtures, and sand-silt
mixtures.
As for fill
material for the dam, preferably, enough suitable material can be
found close to the site so that it's not necessary to bring material
in that adds to expenses. Fill material can be taken from the reservoir
area, leaving the surrounding landscape undisturbed and borrow areas
will not be visible. Generally, soils that are acceptable as foundation
material also make good fill material.
Spillways are
a necessary part of embankment pond construction in order to avoid
a breach in the dam. In ponds of 10 acres or less, a vegetated spillway
is sufficient to control runoff during rainstorms. Ponds larger
in size should have a principal spillway in addition to a vegetated
spillway. The principal spillway should be designed with a pipe
inlet that controls the pond level, provides drainage for pond repairs,
and allows water to escape without erosion.
Building
an earthfill dam
| Foundation |
A safe
earthfill dam can be built on almost any foundation if you
thoroughly investigate the foundation and adapt the design
and construction to the conditions. However, keep in mind
that the cost of construction on less desirable foundations
may not be justified for smaller ponds.
Good
foundations consist of soil underlain at a shallow depth by
a thick layer or relatively impervious consolidated clay or
sandy clay. In this case, topsoil can be removed and scarified
or disked to provide a bond with the material in the dam. |
| Cutoff |
If the
dam's foundation is covered by alluvial deposits of pervious
sands and gravels at or near the surface and rock or clay
at a greater depth, seepage in the pervious material can be
reduced by installing a cutoff or core trench.
A cutoff
is most commonly made of compacted clayey material. A trench
is excavated along the centerline of the dam deep enough to
extend well into the impervious layer. This trench also extends
into and up the abutments of the dam as far as there is any
pervious material that might allow seepage. The trench is
filled with successive thin layers of clay or sandy clay material,
which is compacted thoroughly before placing the next layer. |
| Top
width and alignment |
Following
are recommended minimum top widths for earth embankments:
Height
of dam (ft) |
Minimum
top width (ft) |
Under
10 |
6 |
11
to 14 |
8 |
15
to 19 |
10 |
20
to 24 |
12 |
25
to 34 |
14 |
Depending
on the situation, a curved alignment is more desirable than
a straight alignment. Curved alignments will retain existing
landscape elements, reduce the apparent size of the dam, and
blend the dam into surrounding natural landforms. |
| Side
slopes |
The side
slopes of a dam depend primarily on the stability of the fill
and on the strength and stability of the foundation material.
The more stable the fill material, the steeper the side slopes,
however, keep in mind that you may be mowing those
side slopes.
Slopes
should not be steeper than shown below, but they can be flatter
as long as they provide surface drainage.
| |
Slope |
| Fill
material |
Upstream |
Downstream |
| Clayey
sand, clayey gravel, sandy clay, silty sand, silty gravel |
3:1 |
2:1 |
Silty
clay, clayey silt |
3:1 |
3:1 |
|
| Settlement
allowance |
To
allow for settlement, build earth dams somewhat higher than
the design dimensions. Most foundations are yielding, and settlement
may range from 1 to 6 percent of the height of the dam, mainly
during construction. |
| Estimating
the volume of the earthfill |
Estimate
the number of cubic yards of earthfill required to build the
dam. The estimate should include:
- volume
in the dam itself including the allowance for settlement,
- volume
required to backfill the cutoff trench,
- volume
required to backfill stream channels or holes in the foundation
area, and
- any
other volume of earthfill the contractor is required to
move
|
Unless you
have all the necessary equipment, you will probably want to employ
a contractor to build your pond. Have a set of drawings and specifications
ready to show the contractor what is to be done.
Drawings should
show all elevations and dimensions of the dam, the dimensions and
extent of the cutoff trench and other areas requiring backfill,
the location and dimensions of the spillways, and any other pertinent
information.
Specifications
should give all the information not shown on the drawing that is
necessary to define what is to be done, prescribe how the work is
to be done if such direction is required, specify the quality of
material and workmanship required, and define the method of measurement
and the unit of payment for the various items of work that constitute
the whole job. |
|
Excavated
Ponds
Excavated ponds
are the simplest to build in relatively flat terrain. They are practical
where the demand for water is small since their size is obtained
by excavation. They are popular due to the ease with which they
can be constructed, their compactness, their relative safety from
flood-flow damage, and their low maintenance requirements.
There
are two types of excavated ponds. One is fed by surface runoff and
the other is fed by ground water aquifers. Excavated ponds fed by
runoff can be used in areas of comparatively flat, but well-drained
terrain, in a broad natural drainageway, or in the low point of
a natural depression. Those fed by ground water aquifers should
be located only in areas of flat or nearly flat topography where
the permanent water table is within a few feet of the surface.
 |
Determining
the soil type at the location of an excavated pond is an important
part of the planning and design process. Soil borings, like
I mentioned for the embankment ponds, can be done for this step.
If the pond will be fed by surface runoff, enough impervious
soil at the site is essential to avoid excess seepage. Fine-textured
clay and silty clay that extend well below the proposed pond
depth make the most desirable sites. Avoid soils underlain by
limestone, which can contain crevices, sinks, and channels.
Observe other ponds in the area of your proposed site. If they're
not holding water like they should, well... |
For ponds fed
by water-bearing sand or sand-gravel layer, the layer must be thick
enough and permeable enough to yield water at a rate that satisfies
the maximum expected demand for water and overcomes evaporation
losses. This layer should also be at a depth that can be reached
practically and economically - not more than 20 feet. Test holes
drilled at intervals over the site will help indicate the normal
water level in the completed pond (Check these holes during drier
seasons too, to avoid being misled by temporarily high water tables).
If you locate
an excavated pond fed by surface runoff on sloping terrain,you can
use a part of the excavated material for a small low dam around
the lower end and sides of the pond to increase its capacity. An
auxiliary spillway will be necessary to pass excess storm runoff
around the dam. Ponds excavated in areas of flat terrain generally
require constructed spillways.
Excavated ponds
can be built in almost any shape, but rectangular is most common
in areas of flat terrain. It is simple to build and can be adapted
to all kinds of excavating equipment. The rectangular form can be
edge shaped with a blade scraper to create an irregular shape that
blends in with the surrounding landscape.

Plan
the placement or disposal of waste material excavated from the pond
in advance of construction operations. Waste material can be stacked,
spread or removed from the site, depending on the situation. If
not removed from the site, it can prove very functional by screening
undesirable views, buffering noise and wind, filling in low areas
in nearby fields, or improving the site's suitability for recreation.
Steps
to building an excavated pond:
Clear
the pond area of all undesired vegetation. Mark the outside
limits of the proposed excavation with stakes. On the stakes indicate
the depth of cut from the ground surface to the pond bottom.
Excavate
and place the waste material as close as possible to the
lines and grades staked on the site.
Seal
the pond to prevent excessive seepage. There are several methods
of doing this:
| Compaction
- this method can be used when the soil contains a wide range
of particle sizes and enough clay (10% or more) and silt to
effect a seal. It's the least expensive method, and the procedure
is simple: remove rocks and tree roots, fill holes and crevices
with impervious material, and roll the soil to a dense, tight
layer. |
| Clay
blankets - pond areas containing high percentages of
coarse-grained soils that lack enough clay to prevent excessive
seepage, can be sealed by blanketing. Blankets should consist
of well-graded material at least 20% clay and cover the entire
area over which water is to be impounded. Spread the material
in layers, 6 to 8 inches thick, and compact each one thoroughly.
|
| Bentonite
- in soils containing high percentages of coarse-grained particles
and not enough clay, bentonite helps reduce seepage. Bentonite
is a fine-textured colloidal clay. It absorbs several times
its own weight in water and, at complete saturation, swells
as much as 8 to 20 times its original volume. Bentonite has
its drawbacks, however. It does swell to the point of near imperviousness,
but when it dries, it returns to its original volume, leaving
cracks. If the water level for a pond fluctuates widely, this
is probably not the best sealing method to use. |
| Chemical
additives - due to the structure or arrangement of clay
particles, seepage if often excessive in fine-grained clay soils.
If these particles are arranged at random with end-to-plate
or end-to-end contacts, they form an open, porous, or honeycomb
structure; the soil is said to be aggregated. Applying small
amounts of certain chemicals to porous aggregates collapses
the open structure and rearranges the clay particles thereby
reducing soil permeability. The chemicals used are called dispersing
agents. Chemical treatment is not effective in coarse-grained
soils. |
| Waterproof
linings - polyethylene, vinyl, butyl-rubber membranes,
and asphalt-sealed fabric liners are gaining wide acceptance
as linings for ponds because they virtually eliminate seepage
if properly installed. Some linings are more expensive than
others, and some age better than others, however all are highly
vulnerable to punctures. Be extremely careful when installing
them. |
Establish
vegetation soon after construction, preferably native varieties.
Trees, shrubs, grasses, and forbs provide erosion control, screening,
space definition, climate control, and wildlife habitat.
|